– Garage Completed.
– Garage Floor: The garage floor will go in by the end of this week, giving it that perfect finishing touch.
– Plumbing: We aim to kick off our plumbing work at the beginning of next week or shortly after.
– Gas Line: Daniel is all set to handle the gas line next week, ensuring everything is safe and ready.
– Garage Door Installation: Mark your calendars for October 17th! On this day, 4T will be installing our brand-new garage door.
– Gutters by Classic Gutters: Sarah has reached out to Classic Gutters to get the installation timeline, and according to Adam, we can expect the gutters to be installed next week.
– A/C Installation: James Heating Cooling and More are on board to install our air conditioning system, keeping us comfortable all year round.
– Septic Reconnection: Troy will be working on reconnecting the septic system next week.
– Final Fit ‘n’ Finish: We’ve decided to hold off on the final fit ‘n’ finish until the water is in, ensuring everything is perfect.
– Thornton’s Visit: We’re looking forward to having Thornton on-site next weekend (fingers crossed), so mark your calendars!